2019

New measure 

Maintenance at the GRMS Inzenham

From 05 August 2019, 7 a.m., to 08 August 2019, 5 p.m.

Interruption of all entry- and exit capacities in Inzenham-West USP.


Testing of the compressor station Haiming

08.,09.,15. and 16. July 2019 (each day from 8:30 a.m. to 2:30 p.m.)

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


Maintenance work at the compressor station Haiming

23.07.2019 7a.m.-6p.m. and 24.07.2019 7a.m.-6p.m

Capacity reduction for the gas transport from the market area NCG (Germany) to the UGS Haidach.

The maximum possible flow (injection/withdrawal) for firm (FZK) and interruptible capacity is 1,785,437 kWh/h.

BZK (short-haul) capacity is not affected. 


Update: precise dates now specified
Construction work: Integration of new pipeline at GRMS Amerdingen

From 05 August 2019 to 25 August 2019

This measure can increase the interruption probability of interruptible exit-capacities in Überackern 2, USP Haidach, Haiming 2-RAGES/bn, Haiming 2-7F/bn, Inzenham-West USP and Wolfersberg USP.


Test of GRMS Amerdingen

Update:

20.5.-22.5.2019 each day 7am – 5pm

This measure can increase the interruption probability of interruptible exit-capacities in Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

2018

09.07.2018, 6 a.m. – 20.07.2018, 12 p.m.:

Integration of Monaco pipeline - new status: now:

09 July 2018, 6 a.m. – 17 July 2018, 6 p.m.: Integration of Monaco pipeline. For details see below.


23.04.2018, 0 a.m. - 25.06.2018, 12 p.m.: Integration of Monaco pipeline

  • This measure will not affect capacities at Haiming 2-RAGES/bn and Haiming 2-7F/bn.
    Furthermore, it will also not affect firm freely-allocable (FZK) entry and firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.
  • Interruptible exit capacity at USP Haidach and Überackern/Überackern 2 will remain unaffected by this measure as long as the total amount of booked and nominated interruptible exit capacity at USP Haidach and Überackern/Überackern 2 does not exceed 4.006.800 kWh/h.

(For Entry nominations using freely-allocable capacities (firm or interruptible) at Überackern, Überackern 2 and USP Haidach in sum a maximum flow of 4.006.800 kWh/h (depending on the pressure delivered by the storage operator at USP Haidach) will be possible)


09.07.2018, 6 a.m. – 17 July 2018, 6 p.m.: Integration of Monaco pipeline (status changed from 20.07.2018, 12 p.m. to 17 July 2018, 6 p.m.)

  • All flows at Haiming 2-RAGES/bn and Haiming 2-7F/bn will be interrupted.
  • This measure will not affect firm freely-allocable (FZK) entry and firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.
  • Interruptible exit capacity at USP Haidach and Überackern/Überackern 2 will remain unaffected by this measure as long as the total amount of booked and nominated interruptible exit capacity at USP Haidach and Überackern/Überackern 2 does not exceed 4.006.800 kWh/h.

(For Entry nominations using freely-allocable capacities (firm or interruptible) at Überackern, Überackern 2 and USP Haidach in sum a maximum flow of 4.006.800 kWh/h (depending on the pressure delivered by the storage operator at USP Haidach) will be possible)


04.07.2018, 7 a.m. – 6 p.m.: Testing of the compressor station in Haiming

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


05.07.2018, 7 a.m. – 6 p.m.: Testing of the compressor station in Haiming

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


10.07.2018, 7 a.m.  – 11.07.2018, 6 p.m.: Construction of GRMS Burghausen-Ort

  • This measure will not affect firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.
  • Firm freely-allocable (FZK) entry and interruptible entry and exit capacity at USP Haidach and Überackern/Überackern 2 will be interrupted.


Please note:
The integration of the compressor station in Wertingen (below) has already been completed and will cause no further interruptions (status 30 October 2018, 11 a.m.).


Construction work: Integration of compressor station Wertingen: 

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

New time frame:

1. Period 10.10.2018, 7 a.m. – 11 p.m.
2. Period 11.10.2018, 7 a.m. – 11 p.m.
3. Period 22.10.2018, 7 a.m. - 01.11.2018, 12 p.m.
 

2017

From 4th April 2017, 9 a.m., to 4th April 2017, noon
Emergency shutdown of the station Kiefersfelden
All exit flows for Kiefersfelden at the zone Kiefersfelden-Pfronten will be interrupted.


From 4th April 2017, 1 p.m., to 4th April 2017, 4 p.m.
Emergency shutdown of the station Brannenburg
All exit flows for Kiefersfelden at the zone Kiefersfelden-Pfronten will be interrupted.


From 3rd May 2017, 7 a.m., to 3rd May 2017, 6 p.m.
Testing of the compressor station in Haiming
This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


From 4th May 2017, 7 a.m., to 4th May 2017, 6 p.m.
Testing of the compressor station in Haiming
This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


From 4th May 2017, 9 a.m., to 4th May 2017, noon
Emergency shutdown of the station Forchheim
This measure can now be conducted without any effects on capacities.


From 13th June 2017, 8 a.m. to 3 p.m. and from 14th June 2017, 8 a.m. to 3 p.m.
Maintenance at the GRMS Amerdingen
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.


Changed time frame: From 21st August 2017 to 31st August 2017, 4 p.m.
Construction of GRMS Finsing 2
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.


From 12th October 2017, 9 a.m., to 12th October 2017, noon
Emergency shutdown of the station Inzenham
All entry and exit flows at the station Inzenham-West USP will be interrupted.


From 8th November 2017, 1 p.m., to 8th November 2017, 4 p.m.
Emergency shutdown of the station Amerdingen
This measure can increase the interruption probability of interruptible exit-capacities in Überackern and Überackern 2, but there will be no effects at USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.


From 9th November 2017, 9 a.m., to 9th November 2017, noon
Emergency shutdown of the station Lengthal 1
This measure can increase the interruption probability of interruptible exit-capacities in Überackern 2, but there will be no effects at USP Haidach.


From 14th November 2017, 9 a.m., to 14th November 2017, noon
Emergency shutdown of the station Schnaitsee 1
This measure can increase the interruption probability of interruptible exit-capacities in Überackern and Überackern 2, but there will be no effects at USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

2016

20. September 2016 17:50 Uhr

bayernets published two maintenance works for November 2016 at the GRMS Schnaitsee 1. We were able to combine both measures. For this reason the two maintenance measures will be replaced by the following:

From 10th November 2016, 7 a.m. – 6 p.m.

Maintenance at the GRMS Schnaitsee 1

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn.


20. September 2016 12:30 Uhr

Please note:
The below mentioned maintenance work at the GRMS Amerdingen has been cancelled.
There will be no capacity restrictions due to maintenance works.
 


From 30th September 2016, 8 a.m. to 6 p.m.
Maintenance at the GRMS Amerdingen
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 


12th July 2016, 6 a.m. - 6 p.m.

Grid Connection SWM Niederpframmern (Inzenham):
Interruption of all exit capacities at the storage Inzenham-West USP.
The period of the maintenance measure will be limited to 12th July 2016 6 a.m. - 6 p.m. (old staus: had to be extended from 8 a.m. - 5 p.m. to 0 a.m. - 6 p.m.)


10. June 2016 02:30 p.m.

Please note: This maintenance work at the underground storage site Wolfersberg (USP Wolfersberg) has already been completed. We expect no further restrictions due to this measure.

From 2nd June 2016, 07:00 p.m., to 12th June 2016, 11:59 p.m.

Former date: 1st June 2016, 00:00 a.m., to 12th June 2016, 11:59 p.m.

Maintenance at the storage Wolfersberg USP

Interruption of all entry- and exit capacities at the storage Wolfersberg USP.

Please notice: 
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn, Haiming2-RAGES/bn and Inzenham-West USP.


From 25th April 2016, 7 a.m., to 28th April 2016, 5 p.m.

Maintenance at the GRMS Inzenham
Interruption of all entry- and exit capacities in Inzenham-West USP.


Measure postponed:
From 9th May 2016 to 12th May 2016 (every day from 8 a.m. to 5 p.m.)

Former date: 11th April 2016 to 15th April 2016 (3 days within this period)

Maintenance at the GRMS Amerdingen.
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 


Measure postponed:
From 10th May 2016, 8 a.m. to 4 p.m.

Former date: 6th April 2016, 9 a.m., to 26th April 2016, 4 p.m

Rebuilding of electronic systems at the GRMS Amerdingen.
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn, Haiming2-RAGES/bn, Inzenham-West USP and Wolfersberg USP.


From 3rd Mai 2016, 7 a.m., to 3rd Mai 2016, 6 p.m., and from 4th Mai 2016, 7 a.m., to 4th Mai 2016, 6 p.m.
Test of compressor station in Haiming

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.


From 17th May 2016 to 19th May 2016 (1 day within this period)
Maintenance at the GRMS Schnaitsee 1

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 


From 1st June 2016, 00:00, to 12th June 2016, 23:59

Maintenance at the storage Wolfersberg USP

Interruption of all entry- and exit capacities at the storage Wolfersberg USP.


From 12th October 2016, 9 - 12 a.m.
Emergency shutdown at the GRMS Inzenham

Interruption of all entry- and exit capacities in Inzenham-West USP.


From 8th November 2016 to 10th November 2016 (1 day within this period)

Maintenance at the GRMS Schnaitsee 1

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 


From 8th November 2016, 9 - 12 a.m.
Emergency shutdown at the GRMS Amerdingen

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 


From 10th November 2016, 9 - 12 a.m.
Emergency shutdown at the GRMS Schnaitsee 1

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn and Haiming2-RAGES/bn. 

2015

07.10.2015, 9:00 Uhr bis 30.10.2015, 8:00 Uhr

Instandsetzungsarbeiten in der GDRM-Anlage Inzenham und der ihr vorgelagerten Leitung. Im oben angegebenen Zeitraum sind sämtliche Kapazitäten vom und zum Speicher Inzenham (USP Inzenham) unterbrochen.

Aktualisierung am 29.10.2015: Die Massnahme wird bereits um 8:00 Uhr beendet.


07.10.2015, 9:00 Uhr bis 30.10.2015, 17:00 Uhr

Instandsetzungsarbeiten in der GDRM-Anlage Inzenham und der ihr vorgelagerten Leitung. Im oben angegebenen Zeitraum sind sämtliche Kapazitäten vom und zum Speicher Inzenham (USP Inzenham) unterbrochen.


22.09.2015, 07:00 Uhr bis 23.09.2015, 18:00 Uhr

Umbau der Niederspannungshauptverteilung in der Verdichterstation Haiming. Mit der Unterbrechung unterbrechbarer entry- und exit-Kapazitäten (Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn, Haiming2-RAGES/bn) ist zu rechnen.


09.06.2015, 09:00 Uhr bis 11.06.2015, 17:00 Uhr

Überholung eines Regelventils in der GDRM Amerdingen
Mit der Unterbrechung unterbrechbarer Exit-Kapazitäten (in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn, Haiming2-RAGES/bn, USP Wolfersberg, USP Inzenham) ist zu rechnen.


20.05.2015, 07:00 Uhr bis 21.05.2015, 18:00 Uhr

Maßnahmen am Netzknoten Burghausen (Überackern, Überackern 2, USP Haidach, Haiming 2-7F/bn, Haiming 2-RAGES/bn): Wartungsarbeiten in der Verdichterstation Haiming. 
Mit einer erhöhten Unterbrechungswahrscheinlichkeit für unterbrechbare Kapazitäten ist zu rechnen.


20.04.2015, 06:00 Uhr bis 24.04.2015, 18:00 Uhr

Testläufe in der Verdichterstation Haiming.
Mit einer zeitweiligen Unterbrechung unterbrechbarer enty- und exit-Kapazitäten (in Überackern, Überackern 2 und USP Haidach) ist zu rechnen.
 


03.03.2015, 08:00 Uhr bis 16:00 Uhr

Zählertausch in der GDRM Schnaitsee1
Mit der Unterbrechung unterbrechbarer exit-Kapazitäten (in Überackern, Überackern 2, USP Haidach, Haiming2-7F/bn und Haiming2-RAGES/bn) ist zu rechnen.

2014

09.12.2014, 09:00 Uhr bis 15:00 Uhr

Verdichterstation Haiming: 

Maßnahmen am Netzknoten Burghausen (Überackern, Überackern 2, USP Haidach, Haiming 2-7F/bn, Haiming 2-RAGES/bn):
Wiederkehrende Wartungsarbeiten in der Verdichterstation Haiming. Mit der Unterbrechung unterbrechbarer Kapazitäten ist zu rechnen.


07.07.2014, 08:00 Uhr bis 10.07.2014, 17:00 Uhr

Maßnahmen am Netzknoten Burghausen (Überackern, Überackern 2, USP Haidach, Haiming 2-7F/bn, Haiming 2-RAGES/bn):
Wiederkehrende Wartungsarbeiten in der Verdichterstation Haiming. Mit der Unterbrechung unterbrechbarer Kapazitäten ist zu rechnen.


12.05.2014, 07:00 Uhr bis 15.05.14, 17:00 Uhr

Station Inzenham:

Instandhaltungsarbeiten/Druckbehälterprüfungen in der GDMR-Anlage Inzenham-West.
Während der Arbeiten ist der Gasfluss vom und zum Speicher Inzenham unterbrochen.

2013

18.09.2013, Beginn 09:00 Uhr bis 18.09.2013, Ende 16:00 Uhr
Station Amerdingen: Test Notaus-Programme, Ausbau der Qualitätsmeßsonde im Stationseingang. Während der Arbeiten ist der Gasfluss unterbrochen.


16.09.2013, Beginn 08:00 Uhr bis 17.09.2013, Ende 16:00 Uhr
Station Amerdingen: Filterwartung, Arbeiten an der Messung. Während dieser Zeit steht nur die halbe Stationskapazität zur Verfügung.


06.08.2013, Beginn 07:00 Uhr, bis 09.08.2013, Ende 20:00 Uhr
Verdichteranlage Haiming: Das Prozessleitsystem der Verdichteranlage Haiming wird umgebaut. In dem oben genannten Zeitraum steht die Verdichteranlage Haiming nicht zur Verfügung.

2012

15.10.2012 bis 19.10.2012
Instandhaltungsarbeiten/Druckbehälterprüfung in der 
GDMR - Anlage Inzenham - West


17.09.2012 bis 27.09.2012
Einbindungsarbeiten an der GDMR - Anlage Anwalting


17.09.2012 bis 26.09.2012
13.08.2012 bis 31.08.2012
09.07.2012 bis 12.07.2012
UGS Wolfersberg - Revisionsarbeiten

2011

10.05.2011-11.05.2011
GHL Inzenham – Egmating/IE 32 - Reparaturmaßnahme an der Leitung 


04.05.2011-05.05.2011
Verdichterstation Haiming - Umbauarbeiten an der Armaturengruppe/Ausbläser

2010

01.06.2010-30.09.2010
GHL Finsing – Bierwang/FB 10 - Leitungsumlegung in der 
Gemeinde Kirchdorf/Fa. Schletter 


14.05.2010-21.05.2010
Verdichterstation Haiming - Wartungsarbeiten am Elektroverdichter

2009

01.09.2009-30.09.2009
GHL Anwalting – Kissing/AK 13 - Leitungsumlegung bei Derching und Einbau einer Schiebergruppe


26.08.2009-30.09.2009
GHL Ulm - Augsburg/UA 06- Erneuerung der Abzweigschiebergruppe bei Kötz/Günzburg


25.05.2009-12.06.2009
GDMR-Anlage Denkendorf/9802 Molchung der GHL Laimerstadt
Denkendorf

2008

01.04.2008-01.09.2008
GHL Ingolstadt - Augsburg/IA 11 - Umlegung der Leitung/Güterverkehrszentrum Augsburg


01.04.2008-01.09.2008
GHL Egmating - Kissing/EK 26 - Umlegung der Leitung im Bereich
Höhenkirchen


01.04.2008-01.09.2008
GHL Finsing - Bierwang/FB 10 - Leitungsumlegung wegen Neubau der BAB