With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

Plan of measures

Here, we inform you about network development and maintenance measures that could result in temporary restrictions of your capacities.

Latest information

About capacity restricting measures

2018

Construction work: Integration of compressor station Wertingen:

This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

New time frame:

1. Period 10.10.2018, 7 a.m. – 11 p.m.
2. Period 11.10.2018, 7 a.m. – 11 p.m.
3. Period 22.10.2018, 7 a.m. - 01.11.2018, 12 p.m.

10.07.2018, 7 a.m. – 11.07.2018, 6 p.m.: Construction of GRMS Burghausen-Ort

  • This measure will not affect firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.
  • Firm freely-allocable (FZK) entry and interruptible entry and exit capacity at USP Haidach and Überackern/Überackern 2 will be interrupted.


Please note:
The integration of the compressor station in Wertingen (below) has already been completed and will cause no further interruptions (status 30 October 2018, 11 a.m.).

09.07.2018, 6 a.m. – 17 July 2018, 6 p.m.: Integration of Monaco pipeline (status changed from 20.07.2018, 12 p.m. to 17 July 2018, 6 p.m.)

  • All flows at Haiming 2-RAGES/bn and Haiming 2-7F/bn will be interrupted.
  • This measure will not affect firm freely-allocable (FZK) entry and firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.
  • Interruptible exit capacity at USP Haidach and Überackern/Überackern 2 will remain unaffected by this measure as long as the total amount of booked and nominated interruptible exit capacity at USP Haidach and Überackern/Überackern 2 does not exceed 4.006.800 kWh/h.

(For Entry nominations using freely-allocable capacities (firm or interruptible) at Überackern, Überackern 2 and USP Haidach in sum a maximum flow of 4.006.800 kWh/h (depending on the pressure delivered by the storage operator at USP Haidach) will be possible)

09.07.2018, 6 a.m. – 20.07.2018, 12 p.m.:

Integration of Monaco pipeline - new status: now:

09 July 2018, 6 a.m. – 17 July 2018, 6 p.m.: Integration of Monaco pipeline. For details see below.

05.07.2018, 7 a.m. – 6 p.m.: Testing of the compressor station in Haiming

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.

04.07.2018, 7 a.m. – 6 p.m.: Testing of the compressor station in Haiming

This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.

23.04.2018, 0 a.m. - 25.06.2018, 12 p.m.: Integration of Monaco pipeline

  • This measure will not affect capacities at Haiming 2-RAGES/bn and Haiming 2-7F/bn.
    Furthermore, it will also not affect firm freely-allocable (FZK) entry and firm limited-allocable (BZK) entry and exit capacities at USP Haidach and Überackern 2.

  • Interruptible exit capacity at USP Haidach and Überackern/Überackern 2 will remain unaffected by this measure as long as the total amount of booked and nominated interruptible exit capacity at USP Haidach and Überackern/Überackern 2 does not exceed 4.006.800 kWh/h.

(For Entry nominations using freely-allocable capacities (firm or interruptible) at Überackern, Überackern 2 and USP Haidach in sum a maximum flow of 4.006.800 kWh/h (depending on the pressure delivered by the storage operator at USP Haidach) will be possible)