With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

Plan of measures

Here, we inform you about network development and maintenance measures that could result in temporary restrictions of your capacities.

Latest information

About capacity restricting measures

From 14th November 2017, 9 a.m., to 14th November 2017, noon

Emergency shutdown of the station Schnaitsee 1
This measure can increase the interruption probability of interruptible exit-capacities in Überackern and Überackern 2, but there will be no effects at USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

From 9th November 2017, 9 a.m., to 9th November 2017, noon

Emergency shutdown of the station Lengthal 1
This measure can increase the interruption probability of interruptible exit-capacities in Überackern 2, but there will be no effects at USP Haidach.

From 8th November 2017, 1 p.m., to 8th November 2017, 4 p.m.

Emergency shutdown of the station Amerdingen
This measure can increase the interruption probability of interruptible exit-capacities in Überackern and Überackern 2, but there will be no effects at USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

From 12th October 2017, 9 a.m., to 12th October 2017, noon

Emergency shutdown of the station Inzenham
All entry and exit flows at the station Inzenham-West USP will be interrupted.

Changed time frame: From 21st August 2017 to 31st August 2017, 4 p.m.

Construction of GRMS Finsing 2
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

From 13th June 2017, 8 a.m. to 3 p.m. and from 14th June 2017, 8 a.m. to 3 p.m.

Maintenance at the GRMS Amerdingen
This measure can increase the interruption probability of interruptible exit-capacities in Überackern, Überackern 2, USP Haidach, Haiming 2-RAGES/bn and Haiming 2-7F/bn.

From 4th May 2017, 9 a.m., to 4th May 2017, noon

Emergency shutdown of the station Forchheim
This measure can now be conducted without any effects on capacities.

From 4th May 2017, 7 a.m., to 4th May 2017, 6 p.m.

Testing of the compressor station in Haiming
This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.

From 3rd May 2017, 7 a.m., to 3rd May 2017, 6 p.m.

Testing of the compressor station in Haiming
This measure can increase the interruption probability of interruptible entry-capacities in Überackern, Überackern 2 and USP Haidach.

From 4th April 2017, 1 p.m., to 4th April 2017, 4 p.m.

Emergency shutdown of the station Brannenburg
All exit flows for Kiefersfelden at the zone Kiefersfelden-Pfronten will be interrupted.

From 4th April 2017, 9 a.m., to 4th April 2017, noon

Emergency shutdown of the station Kiefersfelden
All exit flows for Kiefersfelden at the zone Kiefersfelden-Pfronten will be interrupted.