Date | Affected Points and Capacity Products | Level of Reduction | Type of Measure | Additional Remarks |
From 02 Apr 2024, 07:00 To 03 May 2024, 17:00 | Uberackern Entry/Exit
| Increased probability of interruption | Maintenance Compressor Station Wertingen | |
From 08 July 2024, 06:00 To 19 July 2024, 19:00 | Wolfersberg USP Exit FZK, bFZK, Interruptible
Inzenham USP Exit FZK, bFZK, Interruptible | FZK Exit reduced to 350 000 kWh/h per storage bFZK Exit reduced to 350 000 kWh/h per storage Interruptible Exit with high risk of interruption | FF01 / FW02 (Finsing) Maintenance | |
From 29 July 2024, 07:00 To 25 October 2024, 07:00 | Wolfersberg USP Exit Interruptible
Inzenham USP Exit Interruptible | Increased probability of interruption | Station Forchheim rebuild | Please note: We do not expect any serious negative impacts on the capacities concerned. |
From 02 September 2024, 07:00
| Uberackern Entry/Exit
| Increased probability of interruption | Maintenance Compressor Station Wertingen |