Plan of Measures

Here, we inform you about network development and maintenance measures that could result in temporary restrictions of your capacities.

Latest Information

About capacity restricting measures

Maintenance Measures / Wartungsmaßnahmen 2026

Date                                                                                                          

 Affected Points and Capacity Products                                                                                                                                                                                                                                                       

 Level of Reduction

 Type of Measure

 Additional Remarks

From 02 February 2026, 07:00


To 20 February 2026, 17:00

Uberackern Entry/Exit
Interruptible, DZK (interruptible)


Uberackern 2 Entry/Exit
Interruptible, DZK (interruptible)


USP Haidach Entry/Exit
Interruptible, DZK/bFZK (interruptible)


Haiming 2-RAGES/bn Entry/Exit
Interruptible, DZK/bFZK/bFZK1 (interruptible)


Haiming 2-7F/bn Entry/Exit
Interruptible, DZK/bFZK (interruptible)

Increased probability
of interruption

Compressor Station Wertingen:

Test & Modification

 

From 13 April 2026, 08:00


To 16 April 2026, 16:00

Inzenham USP Entry / Exit
FZK, bFZK, Interruptible
Interruption of all entry and exit flowsMaintenance of station InzenhamCancelled

From 04 May 2026, 07:00


To 05 May 2026, 17:00

Uberackern Entry/Exit
Interruptible, DZK (interruptible)


Uberackern 2 Entry/Exit
Interruptible, DZK (interruptible)


USP Haidach Entry/Exit
Interruptible, DZK/bFZK (interruptible)


Haiming 2-RAGES/bn Entry/Exit
Interruptible, bFZK/bFZK1 (interruptible)


Haiming 2-7F/bn Entry/Exit
Interruptible, bFZK (interruptible)

Increased probability
of interruption
Maintenance Compressor Station Wertingen