Maßnahmenplan

Wir informieren Sie hier über Netzausbau- und Instandhaltungsmaßnahmen, die vorübergehende Einschränkungen Ihrer Kapazitäten zur Folge haben könnten.

Aktuelle Meldungen

Kapazitätsrelevante Maßnahmen

Maintenance Measures / Wartungsmaßnahmen 2024

Date                                                                                                          

 Affected Points and Capacity Products                                                                                                                                                                                                                                                       

 Level of Reduction

 Type of Measure

 Additional Remarks

From 02 Apr 2024, 07:00

To 03 May 2024, 17:00

Uberackern Entry/Exit
Interruptible, DZK (interruptible)


Uberackern 2 Entry/Exit
Interruptible, DZK (interruptible)


USP Haidach Entry/Exit
Interruptible, DZK/bFZK (interruptible)


Haiming 2-RAGES/bn Entry/Exit
Interruptible, DZK/bFZK/bFZK1 (interruptible)


Haiming 2-7F/bn Entry/Exit
Interruptible, DZK/bFZK (interruptible)

Increased probability
of interruption
Maintenance Compressor
Station Wertingen
 

From 08 July 2024, 06:00

To 19 July 2024, 19:00

Wolfersberg USP Exit

FZK, bFZK, Interruptible

 

Inzenham USP Exit

FZK, bFZK, Interruptible

FZK Exit reduced to 350 000 kWh/h per storage

bFZK Exit reduced to 350 000 kWh/h per storage

Interruptible Exit with high risk of interruption

FF01 / FW02 (Finsing) Maintenance

 

Cancelled

 

 

From 15 July 2024, 06:00

To 19 July 2024, 16:00

 

Uberackern Entry
Interruptible, DZK (interruptible)


Uberackern 2 Entry
Interruptible, DZK (interruptible)

Increased probability
of interruption
Maintenance Compressor
Station Haiming
 

From 29 July 2024, 07:00

To 11 November 2024, 18:00

Wolfersberg USP Exit

Interruptible

 

Inzenham USP Exit

Interruptible

Increased probability of interruptionStation Forchheim rebuild

Please note:

We do not expect any serious negative impacts on the capacities concerned.

From 02 September 2024, 07:00


To 15 October 2024, 17:00

Uberackern Entry/Exit
Interruptible, DZK (interruptible)


Uberackern 2 Entry/Exit
Interruptible, DZK (interruptible)


USP Haidach Entry/Exit
Interruptible, DZK/bFZK (interruptible)


Haiming 2-RAGES/bn Entry/Exit
Interruptible, DZK/bFZK/bFZK1 (interruptible)


Haiming 2-7F/bn Entry/Exit
Interruptible, DZK/bFZK (interruptible)

Increased probability
of interruption
Maintenance Compressor
Station Wertingen
Prolonged by four days from 11 to 15 October