2014: Revenues from capacity allocations as per section 13 para. 1 GasNZV and their utilisation as section 13 para. 4 GasNZV
bayernets GmbH achieved additional revenues in 2014 due to temporary bottlenecks in terms of section 13 para. 4 GasNZV . For the crossboarder point Überackern 2 the given details to auctions at https://primary.prisma-capacity.eu state that these additional revenues are unique. A provision for the purpose of increasing capacity was not formed. As a result the additional revenues from the auctions will be considered reducing the network tariffs.