With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

With our gas transmission system,
we take responsibility for your future:
bayernets – reliable, sustainable & innovative

We are sustainably securing the future of Germany’s economy with our gas infrastructure, ensuring a gas supply our customers can count on – always.

Auction premiums

Revenues from capacity allocations and their use according to section 13 GasNZV.

2013: Revenues from capacity allocations as per section 13 para. 1 GasNZV and their utilisation as section 13 para. 4 GasNZV

bayernets GmbH achieved additional revenues in 2013 due to temporary bottlenecks in terms of section 13 para. 4 GasNZV . For the crossboarder point Überackern the given details to auctions at https://primary.prisma-capacity.eu state that these additional revenues are unique. For the crossboarder point Kiefersfelden/Tirol from 01.10.2013 the marketmodel Austria (Marktmodell Österreich, COSIMA) has come into effect that avoids future short-term contractual congestion. A provision for the purpose of increasing capacity was not formed. As a result the additional revenues from the auctions will be considered reducing the network tariffs.